Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
September 2013 – End of Construction



Friday, May 31, 2013

Water Services to Start Next Week

Woodmere Lane: The contractor completed the water main testing this past week. The contractor also installed storm sewer along Woodmere Lane.

Next week the contractor will complete the storm sewer installation and begin installing water services to each residence.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

Locust Lane: No work is anticipated.

Thank you for your patience during the construction operations.

Friday, May 24, 2013

Woodmere Lane Water Main Completed

Woodmere Lane: The contractor completed the water main installation along Woodmere Lane. The contractor also performed some water main testing.

Next week the contractor will continue to perform water main testing and begin working on storm sewer replacements and installation.

Thank you for your patience during the construction operations.

Locust Lane: No work is anticipated.

Friday, May 17, 2013

Woodmere Lane Water Main Started

Woodmere Lane: The contractor saw-cut the existing pavement and began installing the new water main starting at Glenview Road.

Next week the contractor anticipates completing the water main installation along Woodmere Lane, installing storm sewer, and testing the new water main.

Thank you for your patience during the construction operations.

Locust Lane: No work is anticipated.

Wednesday, May 15, 2013

Woodmere Lane Water Main Shut-Down

The Contractor will be starting the water main installation on Woodmere Lane at Glenview Road tomorrow, Thursday May 16th. The contractor will need to do a water main shut down for the following section:

Areas Affected: Woodmere Lane from Glenview Road to South End.
Day: Thursday, May 16, 2013
Start Time: 9:00 AM
Duration: 6-8 Hours

All affected residents will receive a door hanger on Wednesday, May 15th with further information and details.

Thank you in advance for your patience during this process.

Friday, May 10, 2013

Woodmere Lane Construction to Start Week of May 13th.

Woodmere Lane: The contractor performed storm and sanitary sewer televising along Woodmere Lane.

The week of May 13th, the contractor anticipates to begin saw-cutting the existing pavement, mobilizing equipment, and begin installing new water main. When the contractor begins water main construction, a water main shut down will be required on the first day of construction. Residents will be notified 24 hours in advance of any water main shut-down.

Thank you in advance for your patience during the construction operations.

Locust Lane: No work is anticipated.

Monday, May 6, 2013

Woodmere Lane: The contractor, R.A. Mancini, is anticipating to perform work in preparation of installing the water main. The work includes sanitary and storm sewer televising, saw-cutting, project layout, and mobilization of equipment. 

Locust Lane: No work is anticipated.