Woodmere Lane: Last week the contractor completed the abandonment of the existing water main at Glenview Road and completed some miscellaneous structure adjustments and tasks around the jobsite. A leakage test on the newly installed water main was also completed.
The contractor has a few items to complete prior to being done on Woodmere Lane including site clean-up, grading of lawns, and minor repairs. At this time, the lawns will be graded in preparation for sod; however, sod will not be installed until the Fall when growing conditions are more favorable.
Currently, the contractor will not be working on Thursday, July 4th and is not scheduled to be working on-site on Friday, July 5th.
Once the underground work is 100% completed, the entire roadway will be paved as part of the Village’s 2013 Street Resurfacing Project.
Locust Lane: No work is anticipated.