Woodmere Lane: Last week the contractor complete installing the water services to each home. The contractor also completed some miscellaneous underground utilities improvements to the storm and sanitary sewer system.
Work remaining includes epoxy lining of sanitary sewers, abandoning the existing water main, and trench paving. Trench paving is scheduled to be completed in the next few weeks. The Village is committed to ensuring the open stone trenches are properly maintained until the asphalt pavement can be installed.
The water main abandonment will require a water main shut down. Residents will be notified 24-hours prior to water being turned off.
Locust Lane: No work is anticipated.