Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
September 2013 – End of Construction



Friday, June 14, 2013

Woodmere Underground Utilities Nearly Complete

Woodmere Lane: Last week the contractor complete installing the water services to each home. The contractor also completed some miscellaneous underground utilities improvements to the storm and sanitary sewer system.

Work remaining includes epoxy lining of sanitary sewers, abandoning the existing water main, and trench paving. Trench paving is scheduled to be completed in the next few weeks. The Village is committed to  ensuring the open stone trenches are properly maintained until the asphalt pavement can be installed.

The water main abandonment will require a water main shut down. Residents will be notified 24-hours prior to water being turned off.

Locust Lane: No work is anticipated. 

Thank you for your patience during the construction operations.