Woodmere Lane:
As part of the 2013 Roadway Resurfacing Project, Arrow Road completed the pavement removal process along Woodmere Lane. Minor pavement repairs and concrete work is anticipated to be completed next week. The contractor is anticipating to install the asphalt surface mid to late next week.
Locust Lane: Last week the contractor completed the main line water main installation including making the connection at Crabtree Lane. The contactor also performed storm sewer improvements along the project site.
Next week, the contractor will continue the water main testing. The contractor will also complete the storm sewer improvements. There might be days with no work on-site due to waiting on test results for the water main next week. If all of the required water main tests pass, the contractor will begin installing water services to individual homes late next week.
We would like to extend our appreciation and patience with those residents who had their water shut-off for an extended period of time on Monday evening due to the various breaks in the existing water main.