Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
September 2013 – End of Construction



Monday, July 8, 2013

No work completed on-site

Woodmere Lane: No work was completed.  

The contractor has a few items to complete prior to being done on Woodmere Lane including site clean-up, grading of lawns, and minor repairs. At this time, the lawns will be graded in preparation for sod; however, sod will not be installed until the Fall when growing conditions are more favorable. 

Once the underground work is 100% completed, the entire roadway will be paved as part of the Village’s 2013 Street Resurfacing Project.

Locust Lane: No work is anticipated. 

Thank you for your patience during the construction operations.