Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
September 2013 – End of Construction



Saturday, July 13, 2013

Locust Lane Water Main to Begin Next Week

Woodmere Lane: Last week the contractor performed grading of the existing landscape and installed topsoil. The sod will not be installed until after September to allow for more favorable growing conditions.

The remaining items along Woodmere include making a repair to the storm sewer and asphalt patching around the additional excavations made.

As part of the 2013 Roadway Resurfacing Project, the contractor is anticipating to install the concrete curb & gutter around the island in the cul-de-sac next week. Once the concrete curb & gutter is installed, the roadway will be milled and resurfaced.  

Locust Lane: The contractor is scheduled to begin water main replacement along Locust Lane between Country Lane and Crabtree Lane this week.  A water main shut-down is scheduled on Tuesday, July 16th at 9AM and last 6 to 8 hours for the contractor to make the connection to the existing water main at Country Lane. Residents will be notified via a separate door hanger 24-hours prior to water being turned off. Please be aware, that as construction operations begin, there is always a chance the water main will need to be shut-down in the case of an emergency, likely because the existing water main broke. In these instances, every effort will be made to notified all effect residents as soon as possible. 

Thank you for your patience during the construction operations.