Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
September 2013 – End of Construction



Monday, August 26, 2013

Pavement Removal Completed on Locust Lane

Woodmere Lane:
No work completed on-site last week.

The final step in completing the project will be the installation of sod and installing pavement markings at Glenview Road. Sod will not be installed until after the Labor Day weekend due to more favorable growing conditions.

Locust Lane:

Last week the contractor completed the remaining underground utility improvements and removed the existing asphalt pavement.

Next week, the contractor is scheduled to perform fine grading of the aggregate base course and asphalt paving.

Now that the asphalt pavement is removed, the roadway is essentially a gravel roadway until the new asphalt pavement is installed. The Village is committed to ensuring the roadway is as smooth as possible.

Thank you for your patience during the construction operations.