Woodmere Lane:
No work completed on-site last week.
The final step in completing the project will be the installation of sod and installing pavement markings at Glenview Road. Sod will not be installed until after the Labor Day weekend due to more favorable growing conditions.
Locust Lane:
Last week the contractor completed the remaining underground utility improvements and removed the existing asphalt pavement.
Next week, the contractor is scheduled to perform fine grading of the aggregate base course and asphalt paving.