Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
September 2013 – End of Construction



Friday, August 2, 2013

Water Services to Begin on Locust

Woodmere Lane:
As part of the 2013 Roadway Resurfacing Project, Arrow Road is anticipating to install the asphalt surface layer on Monday, August 5th.  

Locust Lane: Last week the contractor performed water main testing. We anticipate to get the results of those tests early next week. Once the water main tests pass, the contractor will begin installing water services along the project site.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

Thank you for your patience during the construction operations.