Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
September 2013 – End of Construction



Friday, September 20, 2013

Sod Restoration On-Going

Woodmere Lane:

No work performed on-site.

The landscape contractor is currently completing the sod installation on Locust Lane and is anticipated to move to Woodmere Lane early next week.

The contractor will also perform the asphalt patching work at Woodmere and Glenview Road.  

Locust Lane:

Last week the landscape contractor completed the grading and installation of topsoil along the roadway and began installing sod. The sod restoration is scheduled to be completed later this week or early next week.

Once the sod restorations are done, the projects on both roadways will be completed.