Woodmere Lane:
No work completed on-site last week.
The final step in completing the project will be the installation of sod. Depending on the weather conditions, the contractor may begin installing sod next week. Otherwise, the contractor will wait until the weather is cooler for more favorable growing conditions. It is likely the contractor will begin installing sod the week of September 16th.
Locust Lane:
Last week the contractor performed landscape grading along the parkways in preparation for the installation of sod. The landscape grading and topsoil installation is nearly complete. A leak detection test of the new water main was also performed.
On Friday, the paving subcontractor completed the installation of the asphalt surface layer.
Depending on the weather conditions, the contractor may begin installing sod. Otherwise, the contractor will wait until the weather is cooler for more favorable growing conditions. It is likely the contractor will begin installing sod the week of September 16th.
Thank you for your patience during the construction operations.