Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
September 2013 – End of Construction



Friday, May 24, 2013

Woodmere Lane Water Main Completed

Woodmere Lane: The contractor completed the water main installation along Woodmere Lane. The contractor also performed some water main testing.

Next week the contractor will continue to perform water main testing and begin working on storm sewer replacements and installation.

Thank you for your patience during the construction operations.

Locust Lane: No work is anticipated.