Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
September 2013 – End of Construction



Wednesday, May 15, 2013

Woodmere Lane Water Main Shut-Down

The Contractor will be starting the water main installation on Woodmere Lane at Glenview Road tomorrow, Thursday May 16th. The contractor will need to do a water main shut down for the following section:

Areas Affected: Woodmere Lane from Glenview Road to South End.
Day: Thursday, May 16, 2013
Start Time: 9:00 AM
Duration: 6-8 Hours

All affected residents will receive a door hanger on Wednesday, May 15th with further information and details.