Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
September 2013 – End of Construction



Friday, May 17, 2013

Woodmere Lane Water Main Started

Woodmere Lane: The contractor saw-cut the existing pavement and began installing the new water main starting at Glenview Road.

Next week the contractor anticipates completing the water main installation along Woodmere Lane, installing storm sewer, and testing the new water main.

Thank you for your patience during the construction operations.

Locust Lane: No work is anticipated.